December Progress

 

 

Click here www.2-hueys.photoreflect.com to see and purchase event photos of your flight

PAEPAGE567 PAGE568 PAGE569 PAGE570 PAGE571 PAGE572 PAGE573 PAGE574 PAGE575 PAGE576 PAGE577 PAGE578 PAGE579 PAGE580 PAGE581 PAGE582 PAGE583 PAGE584 PAGE585 PAGE586 PAGE587 PAGE588 PAGE589 PAGE590 PAGE591 PAGE592 PAGE593 PAGE594 PAGE595 PAGE596 PAGE597 PAGE598 PAGE599

December 1st - Pouring the entrance floor. December 1st - Forming the areas where walls will be built.
December 1st December 1st - Premier Concrete Coating.
December 1st December 1st
December 1st - Ron Poret & Kevin Adkinson assembling work tables & cabinets. December 4th - The green steel for the tower has arrived.
December 4th - Unloading the steel for the tower. December 4th
December 6th - More window frames are put in the observation tower. December 6th - Window frame work in the observation tower.
December 7th - The view from the Library window. December 7th - You can see the angle the windows will have once installed.
December 7th December 7th
December 11th - The crew from Acoustical ceilings LLC is here to start putting up the steel framework for the interior walls. December 12th
December 12th December 12th
December 12th December 12th
December 13th - The view from the main display area up to the second floor mezzanine. December 13th - The walls on the second floor are going up fast!
December 13th December 13th
December 18th - Plumbing the water system for the heated floors in the hangars. December 18th - Wall studs are going up in the Lobby & bathroom areas.
December 19th - Wall studs around the stair case on the second floor. December 19th - Chris, from MC Contracting, working on the boiler system.
December 19th December 20th - NIPSCO is here to run the gas line to the building.
December 20th December 20th - Digging the trench for the gas line.
December 21st - Trenching for the gas line. December 21st - NIPSCO digging out by Hwy 218.
December 22nd - Natural gas line. December 26th
December 27th - The plumbing continues. December 27th
December 28th - The gas meter is in. December 28th - The curved wall structure in the mezzanine is being installed.
December 28th - View from the main display area up to the second floor mezzanine. December 28th - John Walker sealing up some areas to keep the weather out.
December 29th December 29th - The wall structure is nearing completion