March Progress

1st to the 15th

 

Click here www.2-hueys.photoreflect.com to see and purchase event photos of your flight

PAGEEPAGE567 PAGE568 PAGE569 PAGE570 PAGE571 PAGE572 PAGE573 PAGE574 PAGE575 PAGE576 PAGE577 PAGE578 PAGE579 PAGE580 PAGE581 PAGE582 PAGE583 PAGE584 PAGE585 PAGE586 PAGE587 PAGE588 PAGE589 PAGE590 PAGE591 PAGE592 PAGE593 PAGE594 PAGE595 PAGE596 PAGE597 PAGE598 PAGE599

March 6th - Ready to pour concrete in the maintenance hangar March - This pumper truck can reach out 100 feet.
March 6th - 7:25 a.m. the first cement truck shows up. March 6th - Pouring the floor in the Maintenance Hangar.
March 6th March 6th
March 6th March 6th
March 6th March 6th
March 6th March 6th
March 6th March 6th
March 6th March 6th
March 6th March 6th - Glenn
March 6th - Brady Saylor, AAA Concrete & Excavation March 6th
March 6th March 6th
March 7th March 8th
March 8th March 15th - Ready for Ryan Fire Safety to put in the sprinkler system.
March 15th - Hooking up the electricity to the building. March 15th