National American Huey History Museum

April Progress

 

 

Click here www.2-hueys.photoreflect.com to see and purchase event photos of your flight

PAGEPAGE567 PAGE568 PAGE569 PAGE570 PAGE571 PAGE572 PAGE573 PAGE574 PAGE575 PAGE576 PAGE577 PAGE578 PAGE579 PAGE580 PAGE581 PAGE582 PAGE583 PAGE584 PAGE585 PAGE586 PAGE587 PAGE588 PAGE589 PAGE590 PAGE591 PAGE592 PAGE593 PAGE594 PAGE595 PAGE596 PAGE597 PAGE598 PAGE599

April 3rd April 3rd
April 3rd April 6th
April 7th April 7th
April 10th April 10th
April 10th April 10th
April 10th April 11th
April 12th April 12th
April 13th April 13th
April 14th April 14th
April 14th April 19th
April 19th April 20th
April 21st - Plumbing for the bathrooms is marked. April 21st - Matt Chilcutt, MC Contracting is laying out the plumbing runs.
April 21st - Window is framed up and one door is up. April 25th - Frame for the arched window in the Library.
April 28th - Steel framework is up for the mechanical room, bathroom and office in the Living History Hangar April 28th - Steel framework is up in the Maintenance/Restoration Hangar for the mechanical room, bathroom and office areas.