Concrete in the New Storage Building May 20th & 21st - Floor June 18th, 19th & 20th - Approaches & sidewalks Thank you to all involved! |
May 20th - The first concrete truck from IMI arrives . |
May 20th - Just before 8 a.m. We had quite the crew of volunteers from AAA Excavating & Concrete and JD Concrete working together to get this concrete job done. |
Mid morning and already half way through the building. |
![]() |
![]() |
![]() |
![]() |
Glen Hall is a master with that float. |
Crews from JD Concrete and AAA Excavating & Concrete cleaning their tools. |
By noon all the concrete was in. |
At 2 p.m. they were finishing the surface of the concrete |
![]() |
![]() |
The crew finished at about midnight. |
![]() |
May 21st - Brady Saylor cutting expansion joints |
![]() |
Glen Hall & Brady Saylor |
Beautifully finished concrete floors. |
![]() |
June 18th - The crew from AAA Excavation & Concrete setting the forms for the concrete approach. Front of the building. |
June 18th - Forms for the approach and sidewalk. Rear of the building. |
June 19th - Pouring the concrete approach. |
June 19th - Front approach. |
![]() |
![]() |
June 19th - Rear approach & sidewalk. |
June 20th - Cutting the expansion joints |
![]() |
![]() |
June 20th - All the concrete work is finished. Another fine job by AAA Excavation & Concrete, JD Concrete and IMI. |