Storage Building Site

& Building going up

April 3 to April 8

 

 

Aerial view of the property before the storage building went up

April 8th - Amish crew getting ready to get started.

Drilling the first hole for the 6x6 posts.

Holes are all dug. ready to start setting posts.

They drop a concrete"cookie" in the bottom of each hole.

They made quick work of setting all the posts.

Semi carrying the trusses coming up the drive.

Driver carefully dumping the trusses on the ground.

Posts are ready to be set.

Tying the posts together

Checking for level.

April 9th - Frame work is up. Ready for trusses April 9th
April 13th - The metal roof panel arrive. Unloading the roof panels.
The first truss goes up.  
April 14th April 14th
   
  April 14th - All the trusses are installed.
  April 15th - lean-to shed is added to the south east corner of the building.
April 16th - The metal roof is started. April 16th
High winds stopped the roofing for a few days April 20th - Roofs on.